Wednesday, March 9, 2016




We are 5 weeks out from arrival of spars and sails so pressure is on to install decks and fittings for rig.  Final interior epoxy coat and paint (in some places) is nearly finished allowing the skins to be installed.






































Outstanding tasks:
  1. Spinn. chute
  2. Buoyancy
  3. Bow
  4. Deck, mast gate 95%
  5. Console 
  6. Flooring 
  7. Rudder, keyway, extension, guide 95%
  8. Mast step
  9. Fore and aft ram assembly
  10. Fittings
  11. Keel mount
  12. Cockpit finishing 75%
  13. Hull mods for cleats, splash guard, shear strip installation, shroud attach, cheek block aft spinnaker
  14. paint 15%
  15. Build support structure
  16. Support boat in cradle
  17. Keel work
  18. Trailer 5%
  19. Install to trailer
  20. Mast rig, April 15
  21. Fit out
  22. Water