Saturday, July 25, 2015
Friday, July 24, 2015
Thursday, July 23, 2015
Saturday, June 27, 2015
Add two intermediate deck support beams. Five fore/aft beams will be set into these bulkheads.
Rudder stock base.
Tuesday, June 23, 2015
Tuesday, June 16, 2015
The intermediate frame strips 3.5, 4.5, 5.5, 6.5 ready for laminating. Used DAP Weldwood urea formaldehyde plastic resin glue. Moving ahead with interior we marked positions for: fore and aft cockpit limits for maximum cockpit size, rudder penetration points, deck vertex line, mid section compartment limits, keel location.

Tuesday, June 9, 2015
Station 3 frame will be set at about 10 degrees from vertical to better align with sides of hull. This frame is cut down to 32mm width as well.
Both sides finished along sheer and trimmed with router. Next is to reinstall ropes to adjust beam correctly along entire length and resume with frame work. The transom crack is fixed but fiberglass buildup at the seems will improve that.
Just installed one sheer board and the other is coming up. This will let me remove the upper nasty edge of the hull shell. This used every clamp I could find and put frame work on hold as well. The frame jig works very quickly. I extended the range to stations 3-7 with intermediate frames at 3.5, 4.5, 5.5, 6.5 that are slightly narrower.
- -
Resolve nasty internal surface damage. Coat inside with epoxy. -Setup baseline alignment to confirm hull is in proper shape.- -Build transverse frames in station 3-7 region. 30%
- -Install sheer beams and temporary beams to hold shell at loft positions. 50%
- -Fiberglass the shell to keelson.
- -Stiffen front sections 1-3 with ribbing.
- -Bulkheads, bouyancy cavities, beams.
- -Cockpit, decking.